Real-world examples of project schedule with dependencies examples
Real examples of project schedule with dependencies examples in different industries
Let’s start where most project managers actually live: inside messy, real timelines. Below are real-world style examples of project schedule with dependencies examples across several industries. The goal is to show how dependencies drive dates, risk, and scope in practice.
Software product launch: example of a cross-team dependency chain
Imagine a mid-sized SaaS company planning a new feature rollout. The high-level project schedule with dependencies examples might look like this in your Gantt tool:
- Requirements finalized → UX design: UX cannot begin until the product requirements document is approved. Classic finish-to-start dependency.
- UX design → API design → Backend development: API contracts depend on UX flows. Backend work depends on the API design. If UX slips by a week, everything downstream shifts.
- Backend development ↔ Frontend development: These can partially overlap with start-to-start and finish-to-finish dependencies. Frontend can start once initial API endpoints are stubbed, but final integration testing can’t finish until both sides are complete.
- Development → QA testing → Security review: Testing is blocked until a stable build is available. The security team won’t run penetration tests until QA signs off on basic stability.
- Security review → Deployment → Customer training: Deployment to production depends on passing security checks. Customer training materials depend on final UI text and workflows.
In this example of a project schedule with dependencies, a single late UX decision can push deployment, training, and even marketing launch dates. A realistic schedule will show buffers before security review and launch to absorb these shifts.
Construction project: best examples of hard, physical dependencies
Construction gives some of the cleanest examples of project schedule with dependencies examples because physics doesn’t negotiate. A typical small office build-out might follow this pattern:
- Permits approved → Site preparation: No work can start until the city or county issues permits. This is a regulatory dependency, not just a task link.
- Site preparation → Foundation → Framing: Foundation work depends on site grading and inspections. Framing cannot start until the foundation cures and passes inspection.
- Framing → Electrical rough-in → Drywall: Electricians and plumbers need walls open to install rough systems. Drywall installation depends on these trades finishing and passing inspection.
- Drywall → Painting → Flooring → Final fixtures: Each layer depends on the previous one being complete and dry. You can’t install flooring while painters are still spraying.
Here, the best examples of schedule risk come from inspections. If an inspector is delayed, your entire chain shifts. Smart project managers model these as explicit dependencies with realistic lag times, not vague “TBD” placeholders.
Marketing campaign: overlapping work and soft dependencies
Marketing timelines usually include more flexible, soft dependencies. A product launch campaign might create a project schedule with dependencies examples like:
- Positioning & messaging → Creative concepts: The creative team needs core messaging before drafting concepts.
- Creative concepts → Ad copy → Design assets: Copywriters and designers work in parallel, but final designs depend on approved copy.
- Design assets → Ad trafficking → Campaign launch: Ads can’t be trafficked to platforms until final files are exported in the right formats.
- Campaign launch → Performance data → Optimization: Optimization work depends on data. You might define a dependency like “Begin optimization 7 days after launch” to ensure enough data volume.
In this example of a project schedule with dependencies, you’ll often see start-to-start links: analytics setup can start before the campaign launches, but reporting depends on live data. Dependencies are more about coordination than physical blockers.
HR onboarding program: examples include recurring, template-based schedules
HR teams building standardized onboarding programs often manage dozens of new hires at once. Their best examples of project schedule with dependencies examples tend to be template-driven:
- Offer accepted → Background check → Start date confirmed: Start dates depend on background check clearance. Some companies add a 3–5 business day lag.
- Start date → Equipment provisioning → Account setup: IT provisioning depends on confirmed start dates and role details.
- Start date → Orientation session → Manager 1:1: Orientation is scheduled on fixed days. Manager 1:1s depend on both the employee’s and manager’s calendars.
- Orientation → Role-specific training → First milestone project: The employee can’t start their first real assignment until they complete certain training modules.
These examples of project schedule with dependencies examples are often managed in HRIS or work management tools where each new hire is a separate instance of the same template. The dependency structure stays the same; dates shift based on individual start dates.
IT infrastructure migration: risk-driven dependency mapping
For IT teams migrating systems to the cloud, dependencies are often technical and risk-heavy:
- Network configuration → VPN setup → Access testing: VPN testing depends on network routes and firewall rules being in place.
- Database backup → Data migration → Data validation: Migration cannot start without a verified backup. Validation scripts depend on the migrated schema.
- Application refactoring → Integration testing → Performance testing: Performance testing is blocked until all integrations are functioning.
- User acceptance testing → Change management communications → Cutover: Cutover depends on user sign-off and readiness communications.
In this example of project schedule with dependencies, teams often use dependency matrices to capture which systems rely on others. This is where a schedule is more than a pretty Gantt: it’s a map of technical risk.
Research and policy projects: external dependencies and uncertainty
Nonprofits, think tanks, and public agencies often face external dependencies that are hard to control. Consider a public health research project aligned with guidance from agencies like the Centers for Disease Control and Prevention (CDC):
- Literature review → Study design → IRB approval: Study design depends on the latest evidence. Institutional Review Board (IRB) approval, often guided by standards from organizations like the National Institutes of Health (NIH), is a hard gate before data collection.
- IRB approval → Participant recruitment → Data collection: Recruitment cannot begin before approval; data collection depends on recruitment targets.
- Data collection → Statistical analysis → Draft report: Analysts can’t run final models until the data set is complete and cleaned.
- Draft report → Peer review → Final publication: Publication timing depends on peer reviewers and editorial calendars.
These are some of the best examples of project schedule with dependencies examples where probabilistic durations matter. Smart teams model ranges and scenarios instead of pretending every dependency will clear on the earliest possible date.
How to structure a project schedule with dependencies examples in modern tools
Most teams don’t build schedules in spreadsheets anymore. They use tools like Microsoft Project, Smartsheet, Asana, or Jira because these tools understand dependency logic.
When you set up examples of project schedule with dependencies examples in these tools, you typically:
- Define tasks with durations, not just dates. The tool calculates dates based on dependencies and calendars.
- Link tasks with dependency types: finish-to-start, start-to-start, finish-to-finish, and in rare cases start-to-finish.
- Add lags (e.g., “Start painting 2 days after drywall finishes” to allow drying time).
- Assign resources so you can see when the same person is overbooked across multiple dependent tasks.
A realistic example of a project schedule with dependencies might show that your lead engineer is on the critical path for three projects at once. The tool will flag over-allocation, and you can adjust dependencies or resource assignments before the dates blow up.
2024–2025 trends: how dependencies are changing in modern projects
If you’re building examples of project schedule with dependencies examples today, you’re working in a different world than five years ago. A few trends stand out:
Remote and hybrid work dependencies
Distributed teams add new layers of dependency:
- Time zone overlap becomes a constraint. A code review can’t happen until there’s at least a 2–3 hour overlap between teams.
- Tool access is a real dependency. A designer can’t work if they’re waiting on a license or VPN access.
Many organizations now model these as schedule constraints rather than pretending everyone is available 9–5 in the same time zone.
AI-assisted scheduling and dependency detection
Modern PM tools increasingly use AI to suggest dependencies based on historical projects. For example, if every past marketing project linked “creative brief” to “asset production,” the tool might auto-suggest that link in new projects.
While you should never blindly accept these suggestions, they can surface missing links in your project schedule with dependencies examples. Vendors often highlight these features in their 2024–2025 roadmaps.
Scenario planning and risk-aware dependencies
More teams are using scenario planning: building multiple versions of a schedule to see what happens if a dependency slips. For example:
- Scenario A: Vendor delivers hardware on time.
- Scenario B: Vendor is 2 weeks late.
By comparing these, you can show leadership how vendor performance affects launch dates. This turns abstract dependencies into visible business impact.
Common dependency types shown through examples
To make your examples of project schedule with dependencies examples more realistic, it helps to use the main dependency types in context.
Finish-to-start (FS)
Most common in construction and software. In our construction example, “Foundation complete → Framing starts” is FS. Task B cannot start until Task A is done.
Start-to-start (SS)
Useful when tasks can overlap. In the software launch example, “Backend development starts → Frontend development starts” might be SS with a small lag, so frontend work begins once basic APIs exist.
Finish-to-finish (FF)
Used when tasks must finish together. For a marketing campaign, “Ad design complete → Ad copy complete” might be FF if legal review requires final versions of both at the same time.
Start-to-finish (SF)
Rare, but it appears in shift work. For example, a support team might say, “New support shift starts → Old support shift can finish.” The old shift can’t end until the new one begins.
When you build a project schedule with dependencies examples that show all four types, stakeholders finally understand why a Gantt chart is more than a pretty bar chart.
Practical tips for building better examples of project schedule with dependencies examples
If you need to create training material, templates, or documentation, you’ll want your examples to be realistic, not textbook-perfect fantasies.
- Anchor dependencies to real constraints. In the HR onboarding example, link tasks to actual payroll cycles, orientation dates, and IT SLAs.
- Show cross-team dependencies. In the IT migration scenario, make it obvious where security, networking, and application teams depend on each other.
- Include external parties. Vendors, regulators, and auditors often create the hardest dependencies. Don’t hide them.
- Model uncertainty. For research projects aligned with NIH or academic standards (see Harvard University’s research guidance), represent review cycles as ranges, not single dates.
- Highlight the critical path. In your best examples of project schedule with dependencies examples, show which tasks actually drive the end date. This teaches teams to focus on the right work when things slip.
FAQ about project schedule with dependencies (with real examples)
Q1: Can you give a simple example of a project schedule with dependencies?
Yes. Picture a basic website build:
- Content outline → Draft copy → Final copy
- Wireframes → Visual design → Development
- Development → QA testing → Launch
Each arrow is a dependency. If draft copy is late, final copy and development both move.
Q2: How many dependencies should I include in my schedule?
Include every relationship where a delay in one task would change the start or finish of another. In practice, that means most tasks in a realistic example of a project schedule with dependencies will have at least one predecessor and one successor.
Q3: What are some real examples of bad dependency management?
Common failures include forgetting to link regulatory approvals, underestimating review cycles, or ignoring vendor lead times. For instance, an IT team might schedule a data center migration without linking it to hardware delivery dates, only to discover that shipping delays push the entire cutover.
Q4: How do I explain dependencies to non-technical stakeholders?
Use simple, concrete examples. In construction, “We can’t install windows before the walls exist.” In marketing, “We can’t run ads until we have approved creative.” Then show the same relationships in your Gantt chart so they see how the visual schedule matches reality.
Q5: Where can I learn more about structured project planning?
Look at guidance from organizations that run large, complex programs. For example, the U.S. General Services Administration publishes project and acquisition planning resources, and universities like Harvard share research project management standards that rely heavily on dependencies and phase gates.
By grounding your own templates in these real examples of project schedule with dependencies examples, you give your team something better than theory: a playbook they can actually run.
Related Topics
Real-world examples of project schedule with dependencies examples
Real-world examples of project milestone schedule templates
Practical examples of resource allocation schedule examples for project management
Real-world examples of weekly project schedule template examples that actually work
Real-world examples of annual project schedule examples that actually work
Your Event Is Not Special (But Your Schedule Should Be)
Explore More Project Schedule Templates
Discover more examples and insights in this category.
View All Project Schedule Templates