Change Request Template Examples for Construction

Explore practical examples of change request templates tailored for construction projects to streamline project management.
By Jamie

Understanding Change Request Templates for Construction Projects

In construction project management, change requests are essential documents that help manage alterations to the original project scope, timeline, or budget. These requests ensure that all stakeholders are informed and that any changes are officially documented and approved. Below are three diverse examples of change request templates specifically designed for construction projects.

Example 1: Change Request for Design Modification

In a scenario where the client wishes to modify the architectural design of a building after the project has commenced, a change request is necessary to formalize the alterations.

Context: A client has requested changes to the layout of a commercial building to optimize the space for future tenants.

Change Request Template:

  • Project Name: Downtown Office Building
  • Change Request ID: CR-001
  • Date Submitted: 2023-10-01
  • Requested By: John Doe, Client
  • Description of Change: Modify the interior layout of the second floor to create two additional office spaces.
  • Reason for Change: To accommodate growing tenant needs and maximize rental income.
  • Impact on Project Timeline: Estimated additional 2 weeks.
  • Additional Costs: $15,000 for redesign and construction.
  • Approval Status: Pending

Notes: Ensure all stakeholders receive a copy of the change request. Follow up with a meeting to discuss potential impacts on the project timeline and budget.

Example 2: Change Request for Additional Work

Sometimes, unforeseen circumstances arise that require additional work outside the original project scope. This template helps document such requests.

Context: A construction team discovers underground utilities that need relocation, necessitating additional work.

Change Request Template:

  • Project Name: City Park Renovation
  • Change Request ID: CR-002
  • Date Submitted: 2023-10-05
  • Requested By: Jane Smith, Project Manager
  • Description of Change: Relocate underground utilities to accommodate new landscaping plans.
  • Reason for Change: Discovery of existing utilities during excavation that were not on initial plans.
  • Impact on Project Timeline: Additional 1 week.
  • Additional Costs: $10,000 for utility relocation.
  • Approval Status: Approved

Notes: Document all changes in the project log for future reference. Consider potential impacts on nearby infrastructure and notify the relevant authorities if necessary.

Example 3: Change Request for Material Substitution

In construction, sometimes materials initially specified may become unavailable. This template helps formalize the request for substituting materials.

Context: A supplier has notified the project team that the specified concrete type is out of stock, prompting the need for an alternative.

Change Request Template:

  • Project Name: Residential Housing Development
  • Change Request ID: CR-003
  • Date Submitted: 2023-10-10
  • Requested By: Mark Johnson, Site Supervisor
  • Description of Change: Substitute Type B concrete for Type A concrete for foundation work.
  • Reason for Change: Unavailability of Type A concrete due to supply chain issues.
  • Impact on Project Timeline: No impact.
  • Additional Costs: None, as Type B is within the original budget.
  • Approval Status: Approved

Notes: Ensure that the substituted material meets all required specifications and standards. Update the project documentation accordingly and communicate with the team to ensure everyone is aligned on the changes.